24
          
        
        
          MARCH-APRIL 2014
        
        
          
            d
          
        
        
          
            &
          
        
        
          
            ri
          
        
        
          EXPLOSIVE
        
        
          DEMOLITION
        
        
          
            COURTESY MARCEL SCHROEDER FROM RICHARD LIESEGANG
          
        
        
          
            Record Frankfurt blast
          
        
        
          What is believed to be one of the largest
        
        
          explosive demolition projects ever carried
        
        
          out in Europe was successfully conducted
        
        
          on 2 February to bring down the 116 m
        
        
          (381 ft) tall AfE Tower, formerly occupied by
        
        
          Frankfurt University, in the centre of that
        
        
          German city.
        
        
          According to reports 950 kg (2,090 lb)
        
        
          of explosive charges were set through the
        
        
          tower, built in 1972, for the blowdown,
        
        
          with large filled water tanks positioned
        
        
          inside the building to help control the
        
        
          resulting dust. The University moved
        
        
          out the tower in 2013 and the original
        
        
          intention was to demolish the tower from
        
        
          the top down. Local objections to the
        
        
          length of time required to carry this out,
        
        
          and the noise and disruption the work
        
        
          would cause, led to the change of plan.
        
        
          A 250 m (820 ft) exclusion zone was
        
        
          established around the tower prior to the
        
        
          blast. Two new office blocks will be built
        
        
          once the site is cleared of the resulting
        
        
          debris.
        
        
          Cardem decided to proceed by blasting. Due
        
        
          to the very poor overall condition of the
        
        
          chimneys, the company decided to perform
        
        
          a thorough analysis of the structure. This
        
        
          consisted of running compression tests on the
        
        
          concrete of each of the 12 sides of each of the
        
        
          three chimneys, using magnetic resonance
        
        
          imaging on the concrete reinforcements and
        
        
          performing scans of the bottom parts of the
        
        
          chimneys.
        
        
          This analysis procedure was highly
        
        
          specialised and extremely innovative in the
        
        
          approach to a demolition and was carried out
        
        
          in addition to the usual sight checks of all the
        
        
          structures. The goal of this in-depth survey
        
        
          was to ensure that the technical choices made
        
        
          were the most adapted to the very unusual
        
        
          context of these structures.
        
        
          It identified an incredibly high strength
        
        
          discrepancy on the bottom level all around
        
        
          the chimneys that generated several potential
        
        
          risks. The concrete heel might not support
        
        
          the weight at blast time, concrete hinges were
        
        
          unfit for supporting the chimneys, the two
        
        
          concrete layers might have a tendency to split,
        
        
          different properties of the two layers and
        
        
          finally three to four layers of rebar were not
        
        
          properly aligned
        
        
          
            CUSTOMISING FOR SUCCESS
          
        
        
          Additionally, unstable elements were
        
        
          inspected and removed by a team of rope
        
        
          access technicians specifically selected for this
        
        
          work. This project was a challenging job and
        
        
          therefore drove us to develop specific methods
        
        
          and customized systems.
        
        
          This project was a big success, not because
        
        
          it went very well, but because Cardem was
        
        
          able to explain the client how everything was
        
        
          going to be managed before it happened. Even
        
        
          more, EDF could be shown exactly how the
        
        
          blasting was going to be done and the precise
        
        
          way these chimneys would fall.
        
        
          The requests of our client were threefold:
        
        
          a precise, almost surgical procedure that
        
        
          required four months of studies; a very short
        
        
          demolition phase, with the real job on the
        
        
          chimneys started in September for a blast in
        
        
          October; and finally an overall management
        
        
          of risk to guarantee safety
        
        
          Throughout the project, demolition
        
        
          operations were shown to the client before
        
        
          being performed on site. The client was
        
        
          constantly involved and was confident
        
        
          because, step by step, a virtual overview of
        
        
          what was going to happen next and why as
        
        
          always available. The project was delivered on
        
        
          time and to budget, and most of all, with no
        
        
          lost time incidents.
        
        
          ■
        
        
          
            The final cleared site after the chimneys fell precisely as planned