27
          
        
        
          
            d
          
        
        
          
            &
          
        
        
          
            ri
          
        
        
          MARCH-APRIL 2014
        
        
          EXPLOSIVE
        
        
          DEMOLITION
        
        
          
            Night lights
          
        
        
          Tower block specialist
        
        
          Safedem was recognised
        
        
          for a contract it successfully
        
        
          carried out in the Scottish
        
        
          city of Greenock.
        
        
          
            D&Ri
          
        
        
          reports
        
        
          
            A
          
        
        
          s part of a Regeneration Area project
        
        
          within an area of the Scottish city
        
        
          of Greenock in Inverclyde, which
        
        
          forms part of an estate of mixed mature social
        
        
          housing, client River Clyde Homes (RCH)
        
        
          identified an area for redevelopment through
        
        
          the demolition of blighted housing stock that
        
        
          then would provide a cleared site suitable for
        
        
          redevelopment into a community parkland
        
        
          and open space.
        
        
          Some demolition in the area had already
        
        
          been carried out, but three
        
        
          redundant 15 to 17 storey tower
        
        
          blocks, Melrose, Peebles and
        
        
          Selkirk, remained. RCH decided
        
        
          to demolish these three blocks
        
        
          as part of its regeneration
        
        
          strategy for the area. In order
        
        
          to demolish the 50 m (164 ft)
        
        
          high structures, a demolition
        
        
          contractor was sought with the
        
        
          necessary expertise to carry out
        
        
          all aspects of the complex site
        
        
          operations.
        
        
          After a rigorous tendering
        
        
          process in August 2012,
        
        
          Safedem was employed a principle contractor
        
        
          to execute all aspects of the blowdown and site
        
        
          clearance works for the project.
        
        
          The Belville Street multi-storey blocks in
        
        
          Greenock’s city centre had dominated the
        
        
          city skyline for over 40 years. The structures
        
        
          were built on a significant slope that created
        
        
          a split level ground floor. The slope was such
        
        
          that the structure was 19 storeys on the north
        
        
          elevation but just 16 storeys on the south. A
        
        
          single lane 2.4 m (7.9 ft) access road known
        
        
          as Serpentine Walk bordered the structures
        
        
          to the north – the only separation of the
        
        
          structures from a 40 m (132 ft)
        
        
          drop down a sheer rock face. At
        
        
          the base of the rock face and just
        
        
          14 m (46 ft) from the structures
        
        
          on plan was the main electrified
        
        
          west coast railway line.
        
        
          
            CONSTRUCTION
          
        
        
          Each of the three towers
        
        
          were approximately 32 x 20
        
        
          m (98 x 66 ft) on plan, and
        
        
          approximately 60 m (197 ft)
        
        
          high. The construction was
        
        
          of reinforced concrete and
        
        
          shear wall construction with concrete floors.
        
        
          The shear walls were unusually thin at just
        
        
          100mm (4 inches) thick, making the stability
        
        
          calculations for Safedem’s pre-weakening
        
        
          works extremely challenging. Presented with
        
        
          such structural issues there was only one
        
        
          option – pre-weaken less and drill more (or
        
        
          longer) holes.
        
        
          The structures were further complicated
        
        
          as they consisted of two offset
        
        
          wings on either side of a stiff
        
        
          centre core area that housed the
        
        
          lifts and stairwells.
        
        
          
            BLAST DESIGN
          
        
        
          Given the close proximity of
        
        
          the nearby rock face combined
        
        
          with the difference in heights
        
        
          at ground level, Safedem’s
        
        
          explosives engineer, William
        
        
          Sinclair, had to design a
        
        
          collapse mechanism that would
        
        
          defy gravity by dropping the
        
        
          structures up hill. To combat
        
        
          the difference in ground levels, he pushed the
        
        
          lowest blast floor up to the building’s 5th floor,
        
        
          calculating that the lower floors would crush
        
        
          down and act as a cushion for the collapsing
        
        
          structure above. To direct the structure up
        
        
          hill, delay detonators were used to encourage
        
        
          the structure to ‘walk’ away from the railway
        
        
          line and come to rest up the hill. The direction
        
        
          and rate of collapse was precisely controlled
        
        
          with a total of 6,300 delay detonators ranging
        
        
          from 100 to 2,200 milleseconds. This range of
        
        
          delays effectively broke up the 40,000 tonnes
        
        
          of structures during the collapse in order to
        
        
          
            The Belville Street tower
          
        
        
          
            blocks just before the
          
        
        
          
            triggering of the charges