28
          
        
        
          MARCH-APRIL 2014
        
        
          
            d
          
        
        
          
            &
          
        
        
          
            ri
          
        
        
          EXPLOSIVE
        
        
          DEMOLITION
        
        
          minimise ground vibration to a maximum
        
        
          recorded level of just 7 mm/s peak particle
        
        
          velocity measured at 14 m (46 ft) from the
        
        
          elevation of the structure. This level was well
        
        
          within the 50 mm/s limit specified in the
        
        
          British Standard BS7385 for Measurement of
        
        
          Groundborne Vibration and the US Bureau of
        
        
          Mines (USBM) Air overpressure levels were
        
        
          recorded as being less than 124dB.
        
        
          
            COMMUNITY LIAISON
          
        
        
          Before the demolition could take place
        
        
          Safedem’s dedicated community liaison team
        
        
          had to evacuate over 600 residents from the
        
        
          145 m (475 ft) exclusion zone. Throughout
        
        
          the project the team consulted with residents,
        
        
          commercial properties, schools and churches.
        
        
          To manage the process, the evacuation
        
        
          was divided into zones of approximately
        
        
          200 households – each with a dedicated
        
        
          evacuation team leader. Over 40 Safedem
        
        
          staff carried out the evacuation – making
        
        
          initial contact with residents, coordinating
        
        
          transportation to rest centres and working
        
        
          closely with staff and residents of a large
        
        
          sheltered housing complex.
        
        
          The Safedem team applied established
        
        
          technology in an innovative
        
        
          way to expedite the evacuation
        
        
          process. Throughout the week
        
        
          before the blowdown, each
        
        
          resident was issued with a pass
        
        
          with a bar code. When leaving
        
        
          the zone via the dedicated gates,
        
        
          the barcodes were scanned and
        
        
          the resident’s information was
        
        
          logged as having duly vacated
        
        
          the zone. This information was
        
        
          
            After the blast
          
        
        
          power wash crews to clear roads, footpaths
        
        
          and structures of dust.
        
        
          The blowdown was carried out overnight
        
        
          in arctic conditions. The security staff and
        
        
          police were exceptional and were described
        
        
          by William as being ‘the true heroes of
        
        
          the operation’. Dust suppression water
        
        
          cannons froze but all the staff maintained a
        
        
          tremendous spirit throughout the difficult
        
        
          conditions.
        
        
          Safedem delivered the project on time
        
        
          (and within Network Rail’s tight timeslot) and
        
        
          under budget. The blast design, and Safedem’s
        
        
          assurances that debris would be
        
        
          contained without rolling down
        
        
          the rock face, allowed the client
        
        
          to save a potential expenditure
        
        
          of a £450,000 (US$740,000)
        
        
          provisional sum that had
        
        
          been allowed for rock face
        
        
          stabilisation and netting works.
        
        
          Regeneration manager
        
        
          Russell Smith of client River
        
        
          City Homes said of the project:
        
        
          “ This complex project has been
        
        
          well delivered and RCH has
        
        
          been delighted with Safedem’s
        
        
          attention to detail throughout
        
        
          every step of the project. The breadth of
        
        
          knowledge and experience brought to the
        
        
          project by Safedem at every level within
        
        
          their organisation, from the CEO to the
        
        
          site labour, excelled at every level turn.
        
        
          Teamwork, effective communications and
        
        
          close coordination of all parties meant that
        
        
          site operations were carried out safely and
        
        
          ultimately the demolition programme was a
        
        
          great success.”
        
        
          ■
        
        
          electronically linked to the control room. This
        
        
          process avoided any build-up of residents at
        
        
          the exit gates and dramatically reduced the
        
        
          time taken for gate staff to scan lists of names
        
        
          and check off residents from a list of over 200.
        
        
          The use of established technology in
        
        
          an innovative way undoubtedly helped the
        
        
          evacuation process, which despite the large
        
        
          numbers involved, was completed 45 minutes
        
        
          ahead of schedule.
        
        
          Following the demolition, the team
        
        
          supervised the immediate clean-up process
        
        
          with the deployment of road sweepers and