WORLD
        
        
          DEMOLITION
        
        
          AWARDS
        
        
          2O14
        
        
          
            31
          
        
        
          
            d
          
        
        
          
            &
          
        
        
          
            ri
          
        
        
          DEMOLITION AWARDS SUPPLEMENT 2014
        
        
          This special
        
        
          D&Ri
        
        
          supplement features the shortlisted entries for this year’sWorld DemolitionAwards. Entries were
        
        
          received from around theworld for the various categories up for grabs,meaning that theAwards truly represent the very
        
        
          best the global demolition industry has to offer. Here entries that have been shortlisted for the various Award categories
        
        
          are detailed in alphabetical order
        
        
          CELEBRATING THEBEST
        
        
          
            Brandenburg Industrial ServiceCo.
          
        
        
          Merck Flint River Plant,
        
        
          Albany,Georgia
        
        
          Brandenburgwas contracted to perform the
        
        
          demolition, environmental remediation, and asbestos
        
        
          abatement of the 65,000m
        
        
          2
        
        
          (700,000 ft
        
        
          2
        
        
          ) former
        
        
          Merck Flint River Plant located in Albany, Georgia.
        
        
          The 100 acre site contained over 115,000 tons of
        
        
          contaminated concrete, blocking and asphalt that
        
        
          was transported to local landfills using a large fleet
        
        
          of trucks and Brandenburg’s custom engineered
        
        
          demolition trailers. All had to be properly permitted
        
        
          and licensed to haul specificwaste streams. Five
        
        
          hundred tons of hazardousmaterial was delivered to
        
        
          an incinerator in Texas and 5,000 tons of hazardous
        
        
          material concretewas required to bemoved to Emelle,
        
        
          Alabamawhere it was landfilled.
        
        
          Once abatement was completed, structureswere
        
        
          dismantled following optimal methods to segregate
        
        
          thematerials. This phase included several multiple
        
        
          story buildings, housing elevator shafts 15.3m (50
        
        
          ft) below ground, pipe racks, tank farms, offices, and
        
        
          all underground utilities, foundations and basements.
        
        
          Therewere 1,322 loads of scrap that generated
        
        
          14,900 tons of recyclablematerial. Excavations of
        
        
          several 1.8m (6 ft) thick foundationsmore than 9m
        
        
          (30 ft) deepwere removed.
        
        
          Throughout daily operations Brandenburg
        
        
          maintained a focused crew of 30-40 trained
        
        
          employees and used its fleet of specialised heavy
        
        
          equipment, including eight Liehberr 954 excavators,
        
        
          a Liehberr 924, a KomatsuWA500 loader, a Cat 973
        
        
          track loader, numerous skid steer loaders and 15-20
        
        
          trucks all operating simultaneously. The final stage
        
        
          was backfilling all excavations caused by the concrete
        
        
          removal.
        
        
          The project was completedwithmore than
        
        
          125,000man hoursworkedwith zero lost time
        
        
          accidents and demonstrated environmental
        
        
          conservation, community improvement to health and
        
        
          safety, and a positive impact on the quality of life.
        
        
          Brandenburg enhanced the site for future development
        
        
          and a safe environment for the community.
        
        
          CONTRACTOF THEYEAR
        
        
          
            OVERUS$1.5MILLION
          
        
        
          
            Cantillon Ltd
          
        
        
          100CityRoad, London, UK
        
        
          Cantillon has been shortlisted for the demolition
        
        
          work it carried out as part of a redevelopment project
        
        
          100City Road in London, UK. The largest building,
        
        
          the 9 storey TransworldHouse, was located on City
        
        
          Road alongside the smaller 6 storey Featherstone
        
        
          House 1 and 6 storey SophiaHouse. AlongOld
        
        
          Street, CommunicationHouse at 3 storeys, and
        
        
          the 4 storey Featherstone House 2were located on
        
        
          Featherstone Street. The sitewas a large island in a
        
        
          cluster with amarketing suite for sales for the follow-
        
        
          on stage located on City Road, constructed on a
        
        
          metal framework connected via a raisedwalkway to
        
        
          CommunicationHouse that was open to the public
        
        
          during the initial stage on sitewhile asbestos removal
        
        
          and soft strip took place. Themarketing suitewas then
        
        
          demolished later in the duration of the project.
        
        
          At tender stage the client had approached Cantillon
        
        
          with a demolitionmethodology plan that included
        
        
          an external steel framework supporting building 3
        
        
          (Featherstone House 1) and building 5 (Featherstone
        
        
          House 2) with footings to sit over the area due to
        
        
          be excavated. Thiswould hinder the timetable for
        
        
          completion and incur a high cost to the overall project.
        
        
          The Cantillon team developed an alternative
        
        
          methodology that allowed the client to see a new
        
        
          approach to the demolition phase that used an internal
        
        
          bracing systemwithin the buildings as opposed to
        
        
          using the steel frame suggested by the client. Prior to
        
        
          demolition on building 3 the internal bracing system
        
        
          was implemented.
        
        
          Demolition commenced on one building at a time,
        
        
          using a high reach excavator located in themiddle
        
        
          of the site and continuedwith 30 tonne excavators
        
        
          once down to level two. This continued down to and
        
        
          including ground level slabswhile retaining parts of
        
        
          Featherstone House 1&2.
        
        
          Due to the high volume of foot traffic aswell
        
        
          as two entrance ramps toOld Street tube station,
        
        
          gantry protectionwas in place prior to demolition of
        
        
          cantilevered slab of 100City Road.
        
        
          
            FabioBrunoConstruções Ltda
          
        
        
          Perimetral Viaduct,
        
        
          Riode Janeiro, Brazil
        
        
          Fabio Bruno Construções  has been shortlisted for
        
        
          the Perimetral Bridge demolition in Rio de Janeiro for
        
        
          client Consórcio Porto Rio. To successfully carry out
        
        
          thework, a number of challenges had to overcome.
        
        
          The demolition had to be carried out in a densely
        
        
          populated area in themost central region of the city of
        
        
          Rio de Janeirowith several protected buildings owned
        
        
          by the BrazilianNavy located around and below the
        
        
          bridge structure. At least 95% of all steel beams had
        
        
          to remain intact during the process of implosion or
        
        
          demolition.
        
        
          The first implosion of a 1,200m (3,940 ft)
        
        
          steel and reinforced steel viaduct was performed to
        
        
          minimise impact on traffic, with all preparation for
        
        
          the implosionmadewith traffic flowing. After this
        
        
          implosion, sevenmonthswere available to complete
        
        
          the demolition stretching 5.000m (16,400 ft).
        
        
          A second implosion of a huge post tensioned 300
        
        
          m (985 ft) concrete viaduct was necessary because
        
        
          theWorld Cupwas nearing and the port was located
        
        
          exactly in front of the structure. The street that passed
        
        
          under the viaduct is one of themost important routes
        
        
          out of downtown and Fabio Bruno had only three days
        
        
          after the implosion to clear part of the road and keep
        
        
          traffic flowing, and 20 days to clean the entire area.
        
        
          Protection of all the pipes and cables located
        
        
          below the entire viaduct was required. Some had
        
        
          been in a placemore than 80 years and therewas
        
        
          no specific drawings for these pipes. In addition, no
        
        
          debris could be allowed to fall from the viaduct into the
        
        
          adjacent ocean in some specific areas.
        
        
          More than 40 different demolition scenarios
        
        
          were simulated to achieve the strict project goals
        
        
          set out by the customer, ensuring steel beams
        
        
          survived undamaged, surrounding structureswere
        
        
          not damaged, and that maximum ground vibrations
        
        
          did not damage tunnels and underground pipes.
        
        
          Four different methodologies of demolitionwere
        
        
          also developed and utilised to guarantee the best
        
        
          demolition process along the length of the viaduct.