38
          
        
        
          DEMOLITION AWARDS SUPPLEMENT 2014
        
        
          
            d
          
        
        
          
            &
          
        
        
          
            ri
          
        
        
          RECYCLING& ENVIRONMENTALAWARD
        
        
          INDUSTRIALDEMOLITIONAWARD
        
        
          
            Brandenburg Industrial ServiceCo.
          
        
        
          Merck Flint River Plant,
        
        
          Albany,Georgia
        
        
          Brandenburgwas contracted to perform the
        
        
          demolition, environmental remediation and asbestos
        
        
          abatement of the 65,000m
        
        
          2
        
        
          (700,000 ft
        
        
          2
        
        
          ) former
        
        
          Merck Flint River Plant in Albany, Georgia, that began
        
        
          production in 1952 and closed in 2007.
        
        
          The first stepwas to implement environmental
        
        
          and safety control methods designed to ensure the
        
        
          safety of workers, the public and the environment. A
        
        
          silt fence and gravel leaching systemwere installed
        
        
          to ensure no contaminants left the property or entered
        
        
          the Flint River.
        
        
          The next stepwas to abate all environmental
        
        
          hazards. The 100 acre site contained over 105,000
        
        
          tonnes of contaminated concrete, blocking and
        
        
          asphalt that was transported to local landfills using a
        
        
          large fleet of trucks alongwith Brandenburg’s custom
        
        
          engineered demolition trailers. All had to be properly
        
        
          permitted and licensed to haul specific waste streams
        
        
          - 500 tons of hazardousmaterial was delivered to
        
        
          an incinerator in Texas, 5,000 tons of hazardous
        
        
          material concrete wasmoved to Emelle in Alabama.
        
        
          Several undocumented process lines full of a
        
        
          hazardous product containing formaldehyde were
        
        
          discovered. Brandenburg notified the owner and
        
        
          formulated awork plan to safely drain and remove
        
        
          these. All wastes were closelymonitored, tracked,
        
        
          and properly documented. By identifying, testing,
        
        
          and disposing of these contaminants, Brandenburg
        
        
          eliminated the hazardous waste at this site.
        
        
          Once abatement was completed, structures were
        
        
          dismantled following optimal methods to segregate
        
        
          thematerials. This phase included several multiple
        
        
          story buildings, housing elevator shafts 15m (50 ft)
        
        
          below ground, pipe racks, tank farms, offices, and
        
        
          all underground utilities, foundations and basements.
        
        
          There were 1,322 loads of scrap that generated
        
        
          more than 13,500 tonnes of recyclablematerial.
        
        
          Excavations of several 1.8m (6 ft) thick foundations
        
        
          more than 9m (30 ft) deepwere removed.
        
        
          The final stage was backfilling all excavations
        
        
          caused by concrete removal. The project was
        
        
          completedwithmore than 125,000man hours and
        
        
          zero lost time accidents.
        
        
          The assignment demonstrated significant
        
        
          environmental conservation, community improvement
        
        
          to health and safety, and a positive impact on the
        
        
          quality of life.
        
        
          
            Central Demolition
          
        
        
          FreescaleMotorola facility,
        
        
          East Kilbride, Scotland
        
        
          Central Demolition has been shortlisted for thework it
        
        
          carried out at the 75,000m
        
        
          2
        
        
          (800,000 ft
        
        
          2
        
        
          ) Freescale
        
        
          Motorola plant in East Kilbride, UK. The site contained
        
        
          a large number of bespoke steel-framed buildings that
        
        
          had been added over a period of yearswhere required
        
        
          to facilitate expansion byMotorola and then by
        
        
          Freescale. The biggest difficulties ensued from the fact
        
        
          that none of the buildingswere of similar construction
        
        
          or of consistent height or feature. This resulted in
        
        
          individual risk assessments andmethodologies
        
        
          having to be developed for each, with each removed
        
        
          successfullywith no incidents or injuries occurring.
        
        
          The demolitionworkwas further complicated
        
        
          by the existence of a testing facility adjoining the
        
        
          demolition site that houses highly sensitive testing
        
        
          equipment that could not be compromised under any
        
        
          circumstances. To prevent damage to the equipment
        
        
          Central organised and implemented a vibration
        
        
          monitoring programme that demonstrated that
        
        
          
            DDMDemontageBV
          
        
        
          Cabot BVcarbonblackplant,
        
        
          Rotterdam, TheNetherlands
        
        
          DDM had been taskedwith the removal of two large
        
        
          dryers at the Rotterdam site where Cabot BV produces
        
        
          carbon black. The dryers are being replaced, with
        
        
          the new units already being fabricated on site.
        
        
          Themethod of removing the old and placing back
        
        
          the new dryers was the challenge. After months of
        
        
          contemplation about the best method to do this,
        
        
          Cabot contacted DDM.
        
        
          With an initially small team consisting of a
        
        
          cost and technical engineer DDM took on the job.
        
        
          Themain priorities for the client were safety, short
        
        
          turnaround, very tight spaces and theminimisation
        
        
          of disturbance to the operational plant. Another big
        
        
          issue would be lifts over live process equipment.
        
        
          Cabot and DDMworked out a detailed plan to
        
        
          replace the dryers and a lifting and rigging company
        
        
          were brought in. These became part of the team
        
        
          that DDM lead, with the company responsible for
        
        
          fabrication of the new dryers also involved in the
        
        
          background.
        
        
          All possible hazards were listed by DDM’s HSEQ
        
        
          acceptable vibration levelswere not breached.
        
        
          The site required extensive remediation activity
        
        
          to keep it safe at all times and tomake it suitable for
        
        
          future redevelopment. The network of stainless steel
        
        
          and plastic pipework carried residual risks despite
        
        
          prior cleaning. Central flushed out and visually
        
        
          checked all pipes for sags and possible sites of
        
        
          hazardousmaterials/substances.
        
        
          Another major hazardwas having towork around
        
        
          the phased removal of high and low voltage cables
        
        
          duringworks on site until the supply to the adjacent
        
        
          building could be diverted. The lineswere clearly
        
        
          marked out and pointed out to all employees during
        
        
          their site inductions to avoid accidents and because
        
        
          it was of paramount importance that power to the live
        
        
          building on-sitewasmaintained at all times.
        
        
          Another example of a significant hazardwas
        
        
          ground contamination. Some of the pits andwork
        
        
          areaswere found to be contaminatedwith oil. To
        
        
          resolve this hazard, these areas of groundwere
        
        
          removed separately and carefully, and segregated for
        
        
          cleaning and remediation prior to recycling.
        
        
          WORLD
        
        
          DEMOLITION
        
        
          AWARDS2O14